Project progress on March 30, 2026 HH3 has poured concrete on floor beam t2 and is constructing the 2nd floor column HH4. Poured concrete cos 0.00 under construction of 1st floor column HH5. The 1st floor column concrete has been poured and the 2nd floor floor beams are being constructed HH6. The 1st floor column concrete has been poured and the 2nd floor floor beams are being constructed
See moreProgress of The Interone project in January 2026
See morePROGRESS OF THE INTERONE PROJECT DECEMBER 2025 Building HH3: reached 70% bracing Building HH4 has 85% bracing Building HH5: completed bracing station Building HH6: reached 90% of the basement floor
See morePROGRESS OF THE INTERONE PROJECT NOVEMBER 2025 - Completed the construction of BP pile pressing, completed the beam covering the pile tops for building measures A-HH3,4,5,6 - Completed construction of phase 1 of building A-HH3,4,5,6 - Completed the excavation work of phase 1 of building A-HH5,6 - Completed construction of concrete lining phase 1 of building A-HH 5,6 - Processing and erecting formwork and reinforcing steel for the foundation of buildings A-HH5 and A-HH6 are underway. - Excavation construction of phase 1 of building A-HH3,4 is underway
See moreUpdate on construction progress of The Interone project - October 2025
See moreTo receive detailed information about the project, please leave your information here