More comfortable and stable living space in The Vesta

Event News
20.09.2022
Share

For a house, wall painting is not only a face, but also a skin covering and protecting items inside and outside the house from wind. storms, rain and sunshine. For a project, wall painting is not only the final steps to complete the apartment or project, but also plays a major role in shaping and creating the living space of the residents in project.

Therefore, the process of finishing the outside paint of the project has been focused by Hai Phat, especially at The Vesta project. With all the desire to achieve the criteria of "Social Housing - Quality Trade" for the owner will live here in the future. To understand about this issue, we had a connection and talked to Engineer Phan Dinh Tap - Deputy Director of Project Management The Vesta to learn more about this issue.

Reporter: Yes, it is known that The Vesta project is a social housing project, so please tell us: The process of finishing the project and painting the surface of the project The Vesta is different from the commercial project? If so, what is the difference?

Mr. Phan Dinh Tap: The entire process of finishing The Vesta project, from the paint outside the home and all other items (construction, acceptance, inspection, ...) are in compliance with the standards, the current rules and procedures of the investor - Hai Phat Investment JSC and absolutely no different than other projects of the Company. At The Vesta project, the direct investment rate influenced the selection of construction materials, so we had to weigh and select the materials carefully so as to meet the cost factor without the image. What does the criterion "commercial quality". Finally, there are two paint companies selected as Lutex of Lutex Vietnam Joint Venture Paint Co., Ltd, supplying and executing, secondly the Luxury of International Investment JSC S.T.C supply and construction. These two lines are highly valued in the market by durability, bright colors and reasonable price.
The kindergarten makes bright colors for the whole project space

Reporter: Could you please give details and details about the process of finishing the paint category at the project Vesta?

Mr. Phan Dinh Tap: The painting process at The Vesta Project is well undergone and according to the sequence of construction steps as for the projects that Hai Phat has ever built before. Finishing the exterior wall paint painting through four main steps as follows: Cleaning and surface preparation; primer; layer 1 coating; 2nd grade finishing coat.

Reporter: In these three steps is the most difficult step, sir?

Mr. Phan Dinh Tap: During the process of finishing wall paint, the hardest of three steps is the step cleaning and surface preparation. Because if the surface is not well prepared then all steps will not be complete as expected. First, the wall surface must be cleaned and flattened, with a new plastered surface, sufficient cure time and dry wall. Then we will use abrasives to grind the wall to remove impurities that affect the adhesion of the coating or coating. In addition, grinding the wall to create a flat surface for the wall, using rough sandpaper to re-surface, then clean the dirt with air compressor or rag clean water.
Court V1 is cleaning and surface treatment to prepare for the primer

Reporter: Through investigation, the finishing of the wall paint in the project is very complex and requires high technical requirements. So how do you know, how to manage and supervise the paint work of the technical team?

Mr. Phan Dinh Tap: All paint works and other works are checked and accepted by 3 parties: construction contractor, supervision consultant and project management board; Simultaneously supervised by Technical Planning Department and Inspection Department of Hai Phat Investment JSC. Offices, units often follow up and accept the basic 4 steps as above. Besides, this is the key project of Ha Dong District and Hanoi City. Therefore, the projects of the project are very closely concerned and inspected closely by the Construction Inspectorate, related departments and agencies. It is required to be checked by the Department of Construction when putting items into use. Therefore, the project always ensure the quality, technique and fine art in accordance with current standards.

 Reporter: Estimated, time to complete the paint work of the whole project The Vesta is ever sir?

Mr. Phan Dinh Tap: It is expected that at the end of November 2017, the project will complete the painting of buildings at The Vesta Project. Specific work completion in the courts as follows: Court V1 is cleaning and surface treatment of 50%; V2 is primed outside the house at 70%; V3 has been painted outside the house finished grade 1, grade 2 paint is 60%; Court V4 painted outside the house finished grade 1; V5 has 80% outside grade 1; V6 has painted outside the house is 100% grade 1, paint layer 2 reaches 70%.
Đội kỹ thuật sơn đang tiến hành công tác sơn lớp 2 của tòa V6

Reporter: Yes, thank you for sharing meaningful and practical. I wish you and the staff at The Vesta Project Management your hard-working and persistent spirit to successfully complete the project, marking the development of Hai Phat Group.

So there are only three months left, The Vesta Project will wear new clothes. At The Vesta Project, the Project Management Unit pays much attention to the project completion; In it, wall painting is considered as a face and is one of the determinants of living space of family members. Each wall is painted in accordance with the technical process, carefully and meticulously to retain the durability of the paint. All with the desire to create a beautiful whole for not just each apartment, but also beautiful for the whole project.

Related news

See more Hai Phat Group achieved Top 10 Gold Star National Brands 2025

On the morning of November 1, 2025, the 11th National Brand Gold Star Award ceremony solemnly took place at Ben Thanh Theater, City. Ho Chi Minh. The program is organized by the Vietnam Union of Science and Business Development in collaboration with the Asian Economic Research Institute and the Institute for Survey and Evaluation of Competitiveness Index, in response to Directive 28/CT-TTg of the Government on "Vietnamese people give priority to using Vietnamese goods". This is a prestigious annual event, honoring outstanding brands, businesses, products, services and entrepreneurs across the country, recognizing the great contribution of the business community to the sustainable development of the Vietnamese economy.

See more HAI PHAT GROUP GRATEFUL BEAUTIFUL DAY ON OCTOBER 20 - A JOURNEY OF ENGAGING AND SPREADING LOVE AT WYNDHAM THANH THUY, PHU THO

On the occasion of celebrating Vietnamese Women's Day October 20, with the desire to express gratitude and honor the great contributions of female officers and employees throughout the system, Hai Phat Group organized a 2-day vacation trip at Wyndham Thanh Thuy Resort - Phu Tho. This is not only a meaningful gift for the "loving half" but also a journey of connection and spreading the spirit of solidarity and sharing in the Hai Phat family.

See more The Interone: 60 days and nights affirming bravery and determination to conquer progress

On the morning of October 10, 2025 in Bac Ninh, Hai Phat Group - Investor of The Interone Project solemnly organized the Launching Ceremony of the 60-day and night emulation movement to complete the project's foundation. The event not only marks the important beginning of the construction phase, but also demonstrates the strong determination of the staff, engineers and workers to complete the project on schedule, ensuring quality and absolute safety.